A project manager is preparing to close a project that delivered a new system for a healthcare organization subject to regulatory oversight. The product has been accepted by the users, but the organization must ensure that all regulatory requirements are satisfied before transitioning the system to operations. What should the project manager do to BEST ensure compliance before project closure?
Before closing projects in regulated environments, a formal compliance audit and validation helps confirm that regulatory obligations have been met and prevents unresolved compliance issues from being transferred to operations.
A project manager notices that team members report to functional managers and are only part-time assigned to the project. Authority over resources is shared. Which organizational structure is MOST likely in place?
In matrix structures, authority and resources are shared between functional and project managers, and team members often have dual reporting.
A key customer strongly supports the project but has unrealistic expectations about delivery speed.Why should the project manager actively manage this perception?
Both positive and negative perceptions can be damaging if not managed holistically. A stakeholder with an unrealistic positive perception may become hostile to the project.